The Newman-Crows Landing Board of Trustees voted 4-1 to approve a $5.7 million bid from an Elk Grove-based Bobo Construction, Inc for a classroom project at Von Renner Elementary at last Monday’s Board of Education meeting.
Trustee Lyzette Gonzalez was the lone dissenting vote after she felt concern about the contractor’s history. In January, the Sacramento Business Journal reported that a construction labor union was concerned about the construction firm receiving a $14.8 million contract and said there was a pattern of concerning behavior on projects and paying prevailing wages.
The project at the district’s oldest elementary school will focus on the demolition of nine degraded classroom buildings and transforming it to portable classrooms. It’s a part of several projects that were proposed during a February 2025 special meeting. In the meeting, it was mentioned the funding for the projects would come from $62 million in bond measures.
Some of the projects mentioned that have already been completed include the addition of LED lighting at Bonita Elementary School and an all-weathered at Orestimba High School.
NCLUSD redid its bid last month after district staff found out that five contractors used a non-approved subcontractor that did not meet the district’s timeline in August
However, Bobo Construction was not the lowest bidder for the project, it was Merced County-based Harris Builders, Inc. at $5.5 million. This drew concern from Caralyn Mendoza, former chief business official for NCLUSD, who asked why it’s not recommended for the district to take the lowest bid.
District Superintendent Justin Pruett, in response, said Merced County contractors did not provide important information in their report and didn’t update their bids.